House Construction Timeline & Payment Schedule Calculator
A house built by a hired contractor takes 11.7 months on average from permit to completion in the US (7.4 months for homes built for sale, 14.3 months when the owner builds — Census 2025). Enter your start date and contract sum to get a stage-by-stage timeline with each payment as an amount and a date, plus a calendar file.
How the timeline works
- Enter the start and the sum Your contract sum, or the quote or estimate you saved.
- Set the stages Copy the percentages from your contract or start from the example.
- Get dates and payments Each stage with its date, payment and running total, plus a calendar file.
Average build time (US, 2025)
- Built for sale: 7.4 months
- Hired contractor: 11.7 months
- Owner-built: 14.3 months
NAHB Eye on Housing (2026-09-08)
Example payment stages (England)
- Deposit on signing: 10%
- Foundations: 15%
- Walls and roof structure: 20%
- Roof on, windows in: 15%
- First fix (plumbing, electrics, plaster): 15%
- Second fix and finishes: 15%
- Completion and snagging: 10%
Pay each stage after it is finished and checked — never ahead of the work.
Planning Signal (2026-04-10) · Rates checked on 2026-11-12.
Questions about build time and payments
How long does it take to build a house?
In the US the Census Bureau's 2025 survey shows 7.4 months from permit to completion for homes built for sale, 11.7 months for a house built by a hired contractor and 14.3 months when the owner builds. Permits, weather and design change this.
How should I pay a builder?
In stages, each after the stage is finished and checked, never in advance. A common example in England: a deposit of 10%, then foundations, walls and roof structure, roof and windows, first fix, second fix, and a last payment held until snags are fixed.
How big should the deposit be?
Planning Signal warns against a builder who asks for more than 10–15% upfront. Many contracts start with 10%.
What is retention?
A small share of each payment, often 5%, kept back until defects are fixed: half at completion and half after the defects period of 6–12 months.
Next step
Planning figures, not financial or legal advice. Your signed contract comes first.